Smart Factory Automation
Manufacturing · AutoBuild Motors

Smart Factory Automation

A connected manufacturing floor on Odoo: MRP planning, work-centre tablets, IoT machine signals feeding OEE dashboards, in-line quality checks and predictive maintenance for an automotive parts manufacturer.

Client
AutoBuild Motors
Category
Manufacturing
Platform
Odoo 17 MRP, Quality, Maintenance + IoT
Duration
16 weeks
Team
6 specialists

0%

OEE improvement

0%

less unplanned downtime

0%

less scrap and rework

The system

Machine signals feed OEE and its components, and highlight issues before they stop the line.

Overall equipment effectiveness

78.4%

Shift A · live

89%Availability
91%Performance
97%Quality
Line 2 · body parts

Press #3

Running

82%

CNC-07

Running

76%

Weld W-2

Idle

64%

Paint booth

Running

79%

Assembly A

Down

41%

QC station

Running

88%

Illustrative view with representative data.

The challenge

AutoBuild Motors planned production on spreadsheets and recorded output on paper travellers. Machine downtime and scrap were only measured weekly, and quality issues were found at final inspection, after expensive rework had already happened.

They wanted real-time visibility of every work centre and a closed loop between planning, execution, quality and maintenance.

Problems & solutions

Problem 1

Machines couldn't talk to the ERP

Legacy PLCs used different protocols and had no direct network integration.

How we fixed it

Edge gateways read PLC signals (cycle counts, run/stop states, alarms) and publish them to Odoo through a lightweight IoT service, buffering data when the network drops.

Problem 2

Paper-based shop floor

Operators filled forms by hand and data reached the office a day later.

How we fixed it

Work-centre tablets show work orders, instructions and quality checks; operators start, pause and finish operations with one tap or barcode scan.

Problem 3

Reactive maintenance

Breakdowns stopped lines without warning.

How we fixed it

Vibration and cycle-time anomalies from machine data predict failures and automatically create preventive maintenance requests before breakdowns.

What we delivered

  • Multi-level BoMs, routings and MRP scheduling
  • Work-centre tablets with digital instructions
  • IoT machine data for OEE (availability, performance, quality)
  • In-line quality control points and alerts
  • Predictive and preventive maintenance
  • Real-time production and scrap dashboards

How the system flows

  1. 1Demand planned
  2. 2Work orders released
  3. 3Machines report output
  4. 4Quality checked
  5. 5OEE calculated
  6. 6Maintenance predicted
Impact

Key operating metrics before the project and after go-live.

OEE

+28%
Before61%
After78%

Unplanned downtime

-38%
Before42 hrs/mo
After26 hrs/mo

Scrap rate

-29%
Before4.1%
After2.9%